| Registered No. WB/SC-247 |
No.WB(Part-I)/2005/SAR-348 | |
![]() | ||
|
Extraordinary | ||
|
Published by
Authority | ||
|
| ||
| ASVINA 27 |
WEDNESDAY , OCTOBER 19, 2005 |
SAKA 1927 |
|
|
|
PART I-Orders and Notifications by the Governor of West Bengal,the
High Court,Government Treasury etc. |
|
WEST BENGAL ELECTRICITY REGULATORY COMMISSION NOTIFCATION No.23/WBERC Dated: 18.10.2005 In exercise of the powers conferred by clause (g), clause (v) and
clause (w) of sub-section (2) of section 181 read with sub-section (3) of
section 32 and sub-section (1) & sub-section (4) of section 47 of the
Electricity Act, 2003 (36 of 2003) and all powers enabling on that behalf,
and in supersession of the Regulation issued under Notification No.
11/WBERC dated 12.11.2003 published on February 19, 2004 in the Kolkata
Gazette, Extraordinary, West Bengal Electricity Regulatory Commission
(WBERC) hereby makes the following Regulations.
1. Short Title, Commencement and Interpretation. These Regulations may be called the West Bengal Electricity Regulatory Commission (Miscellaneous Provisions) Regulation, 2005. i) These shall come into force on the date of the publication in the official Gazette unless otherwise stated in these Regulations and shall be concurrent within the area of jurisdiction of West Bengal Electricity Regulatory Commission. ii) The
Bengal General Clauses Act, 1899 (Ben. Act I of 1899) shall apply to the
interpretation of these regulations unless otherwise indicated in these
Regulations or inconsistent with the Provisions of the Electricity Act,
2003. 2.
Definitions. a) The Act means the Electricity Act, 2003; b) Regulation means the Regulation made under the Act; c) Rules means the Rules made under the Act; d) Commission means the West Bengal Electricity Regulatory Commission constituted under Section 82 of the Electricity Act, 2003 and in short called WBERC; e) Words and
expression used and not defined in the Regulations shall have the meanings
as defined in the Act. 3. Fees and Charges of State Load Despatch Centre. Subject to the provisions of Section 32 of the Act, the State Load Despatch Centre may levy and collect the following fees and charges from the generating companies and licensees engaged in transmission of electricity. a) 2 paise per 100 units (kwh) of electricity transmitted through the intra-state grid. b) The fee shall be payable by all the Generating Companies and Licensees quarterly in advance based on estimated electricity to be transmitted by them through intra-state grid and final adjustment will be done annually after the close of the year. c) The Commission may revise the rate of such fees from time to time depending on and keeping in view the financial requirements of the State Load Despatch Centre and the function to be performed by the State Load Despatch Centre. (d) The Commission may also levy any other charge as it may think appropriate and the same shall be collected by the State Load Despatch Centre in the same manner as is applicable for collection of fees. (e) This clause shall come into force when Section 31 of the Act is applicable in the State of West Bengal. 4. Security Deposit. Subject to the provisions of the Act, the distribution licensee may require any person to deposit security deposit with such licensee, an amount covering 3 months of estimated bills of consumption of electricity at the prevailing rates. The estimated consumption shall be based on 12 months consumption of the previous period as on 1st April of each year or estimated consumption based on his application in case of the new applicant. Provided that in the case of a new applicant, the estimated consumption based on his declared load shall be treated as an advance, which shall be appropriately adjusted with the amount of security deposit that would eventually be determined on the basis of his first 12 months consumption when the latter time period is over. i) A consumer, on such licensees demand may replenish the deposit as and when it becomes insufficient and the same shall be done within a period of one month unless otherwise stated in these Regulations. ii) The
security deposit may be deposited either in cash or an irrevocable Bank
Guarantee. The validity of the Bank Guarantee shall be for a period of 2
years with a further claim period of 3 months for lodging the claim. The
Bank Guarantee shall be renewed from time to time well before expiry of
the Bank Guarantee and at least 3 months before the last date of the
validity of the Bank Guarantee excluding claim period. The Bank Guarantee
shall be from a nationalized or a reputed private sector bank or the West
Bengal State Cooperative Bank Limited or a District Central Cooperative
Bank in West Bengal and be issued from a branch preferably which is within
the distribution area of the licensee, but in no case outside the city in
which the distribution licensee operates unless the licensee agrees due to
specific reasons. iv) All bank charges in connection with the Bank Guarantee or Letter of Credit shall be borne by the concerned consumer. v) The security deposit shall be appropriately returned / refunded within 15 days on the request of the person who gave such security deposit after adjusting amount of any outstanding bill. vi) The distribution licensee shall pay interest on cash security deposit equivalent to 6% p.a. Such interest shall be computed annually and added to the security deposit held against the consumer account as long as the security deposit thus held is less than or equal to the amount of required security deposit provided that excess interest amount shall be annually refunded / adjusted to the consumer in the event, the security deposit amount is already sufficient or become sufficient, in the billing month of May of each year. The non-refund or non-adjustment of the interest or security deposit to eligible consumer accordingly shall attract interest @ 10% p.a. in addition to other penalties etc. as per the provisions of the Act and Regulations. vii) Security
deposit for temporary supply shall be based on the estimated quantum of
consumption and the rate of tariff applicable to that category of
consumers to which the person seeking temporary supply falls, in
accordance with the relevant tariff order of the Commission, which is in
force for the time being. Such security deposit shall be paid in cash or
demand draft or bankers cheque in advance before providing the
supply. ix) In case, any electric line or electric plant or electric meter is provided to any consumer exclusively, by the licensee at the licensees cost, then an additional amount equivalent to 25% of such cost may also be added to the security deposit to be furnished by such a consumer. 5. General Powers: (i) The Commission may, at any time at its sole discretion vary, alter, modify, add or amend any provision of this Regulation. (ii) If any difficulty arises in giving effect to any of the provisions of this Regulation, the Commission may for reasons to be recorded in writing direct the distribution licensee or any other person concerned by general or special order, for taking suitable action not inconsistent with the provisions of this Act, as may appear to be necessary for removing the difficulty. 6. Repeal: The West Bengal Electricity Regulatory Commission (Miscellaneous Provisions) Regulation, 2003 issued under Notification No. 11/WBERC dated 12th November 2003, published in the Kolkata Gazette, Extraordinary on 19th February 2004 is hereby repealed. Notwithstanding such repeal, anything done or any action already taken under the repealed regulation, shall in so far as it is not inconsistent with the West Bengal Electricity Regulatory Commission (Miscellaneous Provisions) Regulation, 2005, be deemed to have been done or taken under the corresponding provisions of the West Bengal Electricity Regulatory Commission (Miscellaneous Provisions) Regulation, 2005. Place:
Kolkata. (K.
L.
Biswas) Annexure A
Please strike out inapplicable portion(s) No Objection with Seal of Police Station wherever
applicable To
Sir, I/We have deposited the requisite fee as per WBERC (Recovery of Expenditure for Providing New Connections) Regulation, 2005. A copy of the receipt is enclosed. You are requested to please process the application. I/We undertake to have the wiring carried out by a licensed wiring contractor(s) only. I/We am/are agreeable to make available the Service connection materials as per list if submitted by you (strike out if not applicable). I/We undertake to abide by the safety rules and shall not violate any statutory provision including those related to unauthorized use / pilferage of electricity.
1. Name of the applicant / organization:-
...
(a) Address .. (b) Rough sketch showing important land mark. (to be attached) 6. Land lord of the premises where supply will be provided. (I) (a) Name (b) Address (c) Consumer No.
.(if already a consumer of the licensee (II) Similar information if the premises is held by more than one landlord. 7. I do not have any objection if electricity supply is temporarily provided for .days for purpose to the applicant.
8. Pole No. nearest to the location of intended supply . .. 9. Supply is required for .. days [From .. ..(date) to .. ..(date)] 10. Connected Load KW. 11. Name & Address of representative of licensed Electrical Contractor(s) who is/are responsible for supervising full electrical installation where temporary supply is required. . . .
(1) ... (2) ... (3) ... Seal of Organisation Yours faithfully, (Full signature of the Person at (2) / President or Secretary or Treasurer of the organization applying for temporary supply) By Order of the Commission
|